Calculator · APFC panel size
How much kVAR do you need?
Enter your load and your PF. See the kVAR to reach your target.
kVAR needed
Estimate33kVAR
You need about 33 kVAR to raise PF from 0.78 to 0.99.
AEE series APFC panel, about 35 kVAR.
5 to 18 stages; we size the steps to your load.
- Load
- 50 kW
- PF now → target
- 0.78 → 0.99
- kVAR, exact
- 32.99
- Panel step
- 35 kVAR
Estimate; we confirm the panel size from your bill and load. kVAR = kW × (tan(cos⁻¹ PF now) − tan(cos⁻¹ target PF)).
What to enter
- Running load, in kW. Use your average load. Know only the sanctioned load? Enter it, with how much of it you use.
- Present PF. It is on your EB bill. No PF on the bill? Divide kWh by kVAh.
- Target PF. It starts at 0.99. Change it if you like.
- Welding machines. Tick this if any run on this supply.
- Unbalanced phases. Tick this if big single-phase machines sit on different phases.
How it works
The calculator uses the standard formula:
kVAR = kW × (tan(cos⁻¹ present PF) − tan(cos⁻¹ target PF))
Example: 50 kW at PF 0.78, with a target of 0.99. That needs about 33 kVAR.
The result is then rounded up to a panel size. Our APFC panels run from 4.5 to 150 kVAR. They have 5 to 18 stages; we size the steps to your load. Contactors switch each stage.
kVAR for each kW of load, target PF 0.99
Multiply your load in kW by the figure for your present PF.
| Present PF | kVAR per kW | For 50 kW |
|---|---|---|
| 0.60 | 1.191 | 60 kVAR |
| 0.65 | 1.027 | 51 kVAR |
| 0.70 | 0.878 | 44 kVAR |
| 0.75 | 0.739 | 37 kVAR |
| 0.78 | 0.660 | 33 kVAR |
| 0.80 | 0.608 | 30 kVAR |
| 0.85 | 0.477 | 24 kVAR |
| 0.90 | 0.342 | 17 kVAR |
| 0.95 | 0.186 | 9 kVAR |
What the result means
- Standard load: an APFC panel sized to the result.
- Welding machines: the result is a starting point only. Each welding panel is custom-built for your machines. Send us your machine list.
- Unbalanced phases: you may need phase-wise fine correction. We will check.
- Over 150 kVAR: ask us about a larger panel or multiple panels.
Good to know
- The result is an estimate. We confirm the size from your bill and load.
- A better PF stops the PF penalty. It does not cut the units (kWh) you use.
- To see what the penalty costs you, try the PF penalty estimator.
- More on the panels: AEE series APFC panels.