Skip to content

Estimator · TNERC T.O. No. 6 of 2025

What is the PF penalty costing you?

Three-phase LT III-B and LT V services must keep PF at 0.85 or above. Enter figures from your EB bill to see the penalty in rupees.

Example · LT III-B

Estimate

7%of CC charges

PF 0.78 is 7 steps of 0.01 below 0.85, at 1% a step.

1%1.5%0%0.500.750.851.00PF 0.78
Penalty for each 0.01 below 0.85, by band. Denser shading costs more.
Tariff

Three-phase services only. PF must stay at 0.85 or above.

Your power factor

Between 0.10 and 1.00, for example 0.78.

₹40,000 a bill. Use the "CC charges" line, not the bill total.

12 for monthly bills, 6 for two-monthly bills.

Estimate the penalty

PF penalty · LT III-B

Estimate

₹2,800a bill

Estimated PF penalty: ₹2,800 a bill. About ₹16,800 a year, at 6 bills.

PF used
0.78
Steps of 0.01 below 0.85
7
Rate in your band
1% a step
Penalty
7% of CC charges
A year (6 bills)
₹16,800

7 × 1% = 7%.

1%1.5%0%0.500.750.851.00PF 0.78
Penalty for each 0.01 below 0.85, by band. Denser shading costs more.

A better PF removes the penalty. It does not cut the units (kWh) you use.

Rule: TNERC Tariff Order No. 6 of 2025, clause 3.2.1(b). Estimate; your bill decides.

The rule

The rule is in TNERC Tariff Order No. 6 of 2025, clause 3.2.1(b). It is dated 30 June 2025. It applies from 1 July 2025.

  • Who: three-phase LT III-B and LT V services.
  • The limit: PF must stay at 0.85 or above.
  • PF from 0.75 up to 0.85: 1% of current consumption charges for each 0.01 below 0.85.
  • PF below 0.75: 1.5% for each 0.01 below 0.85. Every step is counted from 0.85, not from 0.75.
  • HT services: PF must stay at 0.90 or above (clause 3.1.1.6).

“One and half percent of the current consumption charges for every reduction of 0.01 in power factor from 0.85”

Clause 3.2.1(b), the line for PF below 0.75.

LT III-B and LT V, three-phase

PF penalty bands for LT III-B and LT V
PF on the billPenalty for each 0.01 below 0.85
0.85 and aboveNone
0.75 to 0.841% of current consumption charges
Below 0.751.5%, counted from 0.85

HT

PF penalty bands for HT services
PF on the billPenalty for each 0.01 below 0.90
0.90 and aboveNone
0.85 to 0.891% of current consumption charges
0.75 to 0.841.5%, counted from 0.90
Below 0.752%, counted from 0.90

In 2024, TNERC removed the old 18.5 kW load limit. Now every three-phase LT III-B and LT V service is covered.

The order also asks for BIS-certified capacitors on larger motors. That means motors and pump sets of 3 HP and above. See clause 3.2.1(a).

What to enter

  • Tariff: LT III-B, LT V (three-phase) or HT.
  • PF: the average PF on your bill. Or enter kWh and kVAh. We work out PF as kWh ÷ kVAh.
  • Current consumption charges: the CC charges on your bill, in rupees (₹).
  • Bills a year: 12 for monthly bills, 6 for two-monthly bills.

Worked examples

An LT III-B service has PF 0.78. Its current consumption charges are ₹40,000. PF 0.78 is 7 steps of 0.01 below 0.85. 7 × 1% = 7%. So the penalty is about ₹2,800 on that bill.

The same service at PF 0.70 is 15 steps below 0.85. Below 0.75 each step costs 1.5%: 15 × 1.5% = 22.5%, about ₹9,000 on that bill.

Welding machines can pull PF far lower. A bill with 1,039 kWh and 5,724 kVAh has PF 0.18: 67 steps below 0.85, 67 × 1.5% = 100.5%. That is more than the consumption charges themselves, as per the order's formula, which sets no upper limit.

Read this before you act

  • This is an estimate. TNPDCL does not publish how it rounds PF. Your bill may differ a little.
  • We last checked the order on 17 October 2026. A newer order may change the rule.
  • A better PF removes the penalty. It does not cut the units (kWh) you use.
  • To fix a low PF, see our APFC panels, or work out the size with the kVAR calculator.
  • Or WhatsApp us a photo of your EB bill.
RYB

Send us a photo of your EB bill

WhatsApp it, call, or send the form. We reply Mon–Sat, 10:00 to 18:00.

Mon–Sat, 10:00 to 18:00. Sunday closed.